If the drive is to be connected to an ABUS crane installation, continue reading. If the drive is to be connected to a different installation: see Connecting the drive to crane installations not made by ABUS.
Compare the operating voltage and frequency range on the type plate with the mains voltage and frequency of the local grid.
Pin multipoint connector on the drive |
Pin multipoint connector on the drive |
Connection cable of drive |
Rectifier for brake |
Insert the connection cable for the drive in the pin multipoint connector on the drive.
Insert the rectifier for the brake in the pin multipoint connector on the drive.
Lay the plug-in connections and connection cable in the connector housing.
Pin multipoint connector on the drive | |
Bush multipoint connector for drive |
Bush multipoint connector for drive |
Insert the bush multipoint connector for the drive on the pin multipoint connector on the drive.
Insert the bush multipoint connector for the brake on the pin multipoint connector on the drive.
Plug-in connection |
Cable bushing |
Screening clamp connection |
Connection cable |
Fasten the connection cable to the screening clamp connection using cable ties.
Lay the plug-in connections and connection cable in the connector housing.
Once the crane installation is ready for operation:
Test the function of the electric trolley.
If the drive runs in the wrong direction:
● Two phases in the power line of the crane installation are interchanged.
If possible, correct the interchanged phases in the power line of the crane installation.
Otherwise:
Switch two phases on the connection cable of the drive.