Installing the ceiling-mounted bracket 2LP/M16 or M20: bolting on with rib nuts

 

The ceiling-mounted bracket 2LP/M16 or M20 is bolted onto its own fastener (customer provided). For this, a pair of M16x70 threaded rods must be available at the site.

 

Ceiling-mounted bracket 2LP/M16 or M20

Minimum spacing of threaded rods

Maximum spacing of threaded rods

Ceiling-mounted bracket A

90 mm

140 mm

Ceiling-mounted bracket B

140 mm

240 mm

Ceiling-mounted bracket C

240 mm

330 mm

 

Threaded rod

Articulated girder

 

Baugröße

The figures show the installation of a ceiling-mounted bracket 2LP/M16 or M20 with projecting threaded rod (with normal suspension, short suspension and normal stiffener). The installation of a ceiling-mounted bracket 2LP/M16 with bolted-on articulated girder (with normal stiffener, inclined suspension, inclined stiffener and V-suspension) does not differ significantly from this.

 

Baugröße

The figures show the installation of a ceiling-mounted bracket 2LP/M16 with bolted-on articulated girder. The installation of ceiling-mounted bracket 2LP/M20 does not essentially differ.

Verweis

The installation of the ceiling-mounted bracket 4LP/M20 is described in the product manual "Installing the ceiling-mounted bracket 4LP/M20 and craneway suspension M20".

 

 

Bolting on the ceiling-mounted bracket 2LP/M16 or M20 with rib nuts

Only with ceiling-mounted bracket 2LP/M16 with articulated girder

This section only applies to the ceiling-mounted bracket 2LP/M16 with bolted-on articulated girder (with normal stiffener, inclined suspension, inclined stiffener and V-suspension)

 

 

Turning the articulated girder

On every ceiling-mounted bracket 2LP/M16 with articulated girder:

The articulated girders can be mounted lengthwise or crosswise to the ceiling-mounted bracket 4LP/M20 as appropriate for the alignment of the supporting structure.

 

Ceiling-mounted bracket

 

 

Articulated girder

*  Insert M16x35 rib screw through articulated girder.

*  Insert articulated girder with rib screw in ceiling-mounted bracket.

*  Screw the M16 rib nut loosely onto the rib screw from the back.

*  Shift the articulated girder lengthwise or crosswise to the ceiling-mounted bracket as necessary.

*  Screw the rib nut on. 300 Nm.

 

 

 

 

On every ceiling-mounted bracket 2LP/M16 or M20:

Planungsunterlagen

Where and at what intervals the ceiling-mounted brackets are fixed to the supporting structure is specified in the planning documents.

The specified dimensions, positions and clearances must be followed exactly.

 

Retaining plates

 

Clamping plate

 

*  Insert retaining plates (2x), ceiling-mounted bracket (1x) and clamping plates (2x) on the threaded rods.

*  Loosely screw the M16 rib nuts onto the threaded rods.

 

 

Ceiling-mounted bracket centred in relation to HB profile rail

Ceiling-mounted bracket perpendicular to HB profile rail

Later-installed HB profile rail

Suspension distance LB

*  Align the ceiling-mounted bracket so that it lies lengthwise exactly perpendicular to the later-installed HB profile rail.

*  Position the ceiling-mounted bracket so that it is exactly centred in relation to the later-installed HB profile rail.

This is necessary so that the HB profile rail can later be aligned.

*  Screw on the M16 rib nuts (2x) initially hand-tight.

The rib nuts will later be tightened to the correct torque (after aligning the HB profile rail).

 

 

If final alignment of the ceiling-mounted bracket 2LP/M16 or M20 can now be done:

*  Screw the rib nuts tight.

The correct tightening torque depends on the bolt quality and the friction coefficient from the standards table.

Example: 200 Nm for M16, bolt quality grade 8.8 and friction coefficient 0.12.