The figures show the installation of a clamping buffer on the flange of an overhead travelling crane ELV. The installation on a lower flange on an overhead travelling crane ELK is very similar.
If the clamping buffers are not installed on the flange or the lower flange:
|
Fillister-head screw |
| |
Rubber buffer |
Clamping buffer |
Rotate the
clamping buffer so that the rubber buffer points towards the trolley.
Push the clamping buffer onto
the flange or lower flange.
Lay one side of the clamping
buffer flat and tighten the fillister-head screw until hand-tight.
Clamping claw |
|
| |
|
Horizontal fillister-head screw |
With the horizontal fillister-head screw, pull the other
side of the clamping buffer onto the flange or lower flange.
Align the clamping buffer so
that both clamping claws are lying flat on the flange or lower flange.
Also ensure that the clamping
buffer has a clearance of at least 5 mm to the profile end or to other
components.
Tighten the horizontal
fillister-head screw. Tighten to 80 Nm.
Tighten both vertical
fillister-head screws. 120 Nm.
| |
Rubber buffer |
|
Push the
rubber buffer down until it lies against the flange or lower flange.