Observe the product manuals! In addition to the points described here, all information in the section “Switching off the crane” in the other supplied product manuals also applies. |
Load hook |
|
| |
Lifting tackle |
|
If possible, set down or remove
lifting tackle (wire ropes, chains, ...) and load lifting attachments
(crossheads, ...).
After the end of work, run the
load hook to just below the highest hook position.
This section is only applicable if the crane can be operated either in a building or outdoors (if the crane track leads out of the building).
Move the crane to the resting
position in the building.
This section only applies if the crane is operated completely outdoors and if it can be secured from wind by means of a falling latch.
Example of a wind anchor at the end of the crane track |
|
|
Set down the load.
If necessary: Set down or remove
the load lifting attachments.
Move the trolley to the left or
right to the end of the main girder.
Move the crane to the resting
position at the end of the crane track.
Run the crane until the falling
latch closes.
Make sure the crane is secured.
This section only applies if the crane is operated completely outdoors and if it can be secured from wind by means of a rail clamp.
Set down the load.
If necessary: Set down or remove
the load lifting attachments.
Switch on the rail clamp.
Make sure the crane is
secured.
Emergency stop switch |
|
|
Press the emergency stop
switch.
For lengthier interruptions:
Mains switch |
Switch off the crane at the
mains switch.